PrepAway - Latest Free Exam Questions & Answers

How many scheduled jobs should you create from Windows Backup?

You have a file server named Server1 that runs Windows Server 2003 Service Pack 2 (SP2).
You need to use Windows Backup to meet the following requirements:
�Minimize the number of scheduled backup jobs.
�Perform a scheduled normal backup to disk every Friday.
.Perform a scheduled normal backup to tape every Friday.
.Perform scheduled differential backups to tape every Monday, Tuesday, Wednesday, and Thursday.
How many scheduled jobs should you create from Windows Backup?

PrepAway - Latest Free Exam Questions & Answers

A.
one

B.
two

C.
three

D.
six