Exam 74-343: Managing Projects with Microsoft Project 2013

Which three actions should you perform in sequence?

DROP
You are a project manager who uses Microsoft Project 2013. A resource manager notifies you that
your assigned resource is now only available 50% to work on the communication plan task. The
estimated amount of work for the task remains the same at 16 hours. The task must also be
completed within the original two-day commitment even though the resource is only available 50%
of the time. You need to bring on another resource to assist with the remaining 50% of the work
while ensuring that the same amount of work gets done in the two days that were originally
committed. Which three actions should you perform in sequence? (To answer, move the appropriate
three actions from the list of actions to the answer area and arrange them in the correct order.)

Which three actions should you perform in sequence?

You are a project manager who uses Project Standard 2013. Your project is approved, and you
identify named resources to replace the generic resources for your project tasks. You need to update
the project schedule to assign the named resources to their appropriate tasks. Which three actions
should you perform in sequence? (To answer, move the appropriate three actions from the list of
actions to the answer area and arrange them in the correct order.)

you need to resolve the over allocation for Resource1 for the month of November only

You are a program manager for a complex software development project. You use Project
Professional 2013 to manage your project. Your resources work on many different projects across
the program, and you need to resolve resource over allocations. Your project team uses a resource
pool to manage resources. Resource1 has been assigned to assist on a project that is on the critical
path. After assigning Resource2 to the task, you notice that Resource1 is over allocated during the
month of November. Project A, which is on critical path, takes priority over Project B, which
Resource1 is also assigned to. Using resource leveling in Project Professional 2013, you need to
resolve the over allocation for Resource1 for the month of November only. What should you do?

You need to ensure that the effort for each resource and task is set up properly in the calendar

You are a project manager for a company that is based in New York and London. The company uses
Project Professional 2013. Teams from both offices are working together on a project. Since the two
offices are located in different regions, the teams have separate company holiday schedules and
working times. You need to ensure that the effort for each resource and task is set up properly in the
calendar. You want to achieve this goal by using the least amount of time and effort. What should
you do?

What happens in the resource pool after you delete the project?

Your company uses Project Professional 2013. You have several projects that are part of a program,
but you do not use Project Server. You use a Resource Pool file to share resources across all projects.
You are informed that one of the projects is cancelled before it starts. As a result, you need to delete
the project. What happens in the resource pool after you delete the project?

You need to monitor this phase closely to ensure that it does not overrun

You are a project manager who uses Project Professional 2013. You are creating a project with
several phases. Your customer requires the delivery phase of the project to start on July 1 and to
finish within four weeks. The delivery phase includes a summary task, which consists of five separate
sub tasks. You need to monitor this phase closely to ensure that it does not overrun. What should
you do?