So what action should you perform to achieve this?

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Microsoft Deployment Toolkit (MDT) 2008 is installed on your computer. The Complete solution option is chosen by you in the process of the setup. You try to use Deployment Workbench to create a new distribution share. But you fail. In order to make your be able to create a new distribution share, the missing software needs to be found out and installed. So what action should you perform to achieve this?

you need to allow project managers to display the life-cycle milestones in their project schedules and compare

Your product development life cycle has defined milestones. A new product launch involves several projects that are published to Microsoft Office Project Server 2007. In Microsoft Office Project Web Access, you need to allow project managers to display the life-cycle milestones in their project schedules and compare them with project start and finish milestones. What should you do?

So what action should you perform?

You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company has computers in two time zones. The company decides to have all the client computers installed with Windows Vista with Service Pack 1 (SP1). Since you are the technical support, the company assigns this task to you. Windows Automated Installation Kit (Windows AIK) is installed by you. You must make sure that in the process of the deployment process, the appropriate time zone setting is configured on each client computer. Meanwhile, you must reduce the number of images of Windows Vista SP1 to the least. So what action should you perform?

What type of view should you create?

In a set of projects that are saved to Microsoft Office Project Server 2007, a custom field is used to indicate project status. You are asked to create a report listing all Active and Completed projects. The report should display graphical indicators to show whether the projects are within budget and schedule. You need to create a view in Microsoft Office Project Web Access so that you can generate this report. What type of view should you create?

You need to create a dynamically numbered representation of the project task hierarchy structure, for use in v

You are working with a project schedule in Microsoft Office Project Standard 2007. Your organization uses customized alphanumeric WBS codes to integrate your project schedules and the accounting system. You need to create a dynamically numbered representation of the project task hierarchy structure, for use in views and reports. What should you do?

Which action should be performed to finish the task?

You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Microsoft Deployment Toolkit (MDT) 2008, Microsoft Systems Management Server (SMS) 2003 with Service Pack 3 (SP3), and Microsoft System Center Operations Manager 2007 are utilized in your company. Zero Touch Installation (ZTI) deployments should be monitored for Windows Vista in your company. Which action should be performed to finish the task?

you need to escalate the risk to an issue, without losing the historical record of the risk

A project that is published to Microsoft Office Project Server 2007 has a risk associated with a task involving delivery of critical parts. You are notified that the parts vendor will be unable to deliver the parts on time, which will delay the entire project by 2 weeks. In Microsoft Office Project Web Access, you need to escalate the risk to an issue, without losing the historical record of the risk. What should you do?