You need to evaluate resource availability for the next six months
You’ve recently approved a project that is scheduled to begin in two months. You need to evaluate resource availability for the next six months. What should you do?
Which action should be performed?
You work as an IT professional in an international corporation named Wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Your company deploys computer images by utilizing Microsoft Deployment Toolkit (MDT) 2008 to. You are making preparations for an image deployment to client computers. Windows Vista and Microsoft Office Word 2007 will be installed by the image. There are many documents owned by the users on your network, and the documents were created with previous versions of Word. Conversion issues should be identified with the documents that were created with previous versions of Word. Which action should be performed?
You need to review all of the work scheduled in all enterprise projects for these resources next week
You manage a project that is saved to Microsoft Office Project Server 2007. You want to verify that the programmers on your team are scheduled to do certain project tasks next week. To ensure that there are no conflicts with other project work, you also want to see the work scheduled for these resources on other projects. You need to review all of the work scheduled in all enterprise projects for these resources next week. What should you do?
You need to evaluate the availability of bike helmet designers for an approved project that will begin in two
You need to evaluate the availability of bike helmet designers for an approved project that will begin in two months. What should you do?
Then what action should you perform?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. Windows Automated Installation Kit (Windows AIK) is used by the company. There is a client computer for you. After you have Windows Vista with Service Pack 1 (SP1) installed on this computer, you make preparation for the image. An image of the client computer needs to be created. Then what action should you perform?
You need to confirm that these resources have no other enterprise project work scheduled for next week
You manage a project that is saved to Microsoft Office Project Server 2007. You want to know whether the programmers on your team have time to work on your project next week. You dont want to interfere with any tasks scheduled for other projects. You need to confirm that these resources have no other enterprise project work scheduled for next week. What should you do?
You need to submit reports that support the management teams requirements for phase classification
You need to submit reports that support the management teams requirements for phase classification. What should you do?
So what action should you perform?
You work as an IT professional in an international corporation named wiikigo. You are experienced in deploying operating system and applications images. And in the company, your major job is to deploy Windows Operating system and troubleshoot everyday issues. The company has client computers deployed with Windows Vista and the 2007 Microsoft Office system by using Microsoft Deployment Toolkit (MDT) 2008. You notice that in the deployment sequence, a specific task is failing. Since you are the technical support, you have to find out the reason for the failure. Therefore, you have to check the appropriate file. So what action should you perform?
You need to create a link that will keep a task in Project B from starting before a specific task in Project A
Two project plans that are published to Microsoft Office Project Server 2007 are interrelated. Both projects have deliverables and resources assigned to tasks. You need to create a link that will keep a task in Project B from starting before a specific task in Project A is complete. What should you do?
You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested r
You need to update the Northwind2U program to reflect the change of resource, and then deliver the requested report. What should you do before you begin the update?