PrepAway - Latest Free Exam Questions & Answers

You have a new server named Server1 that runs Windows Server 2012 R2.

You have a new server named Server1 that runs Windows Server 2012 R2.

Server1 has two dual-core processors and 32 GB of RAM.

You install the Hyper-V server role on Server1.

You create two virtual machines on Server1 that each have 8 GB of memory.

You need to minimize the amount of time it takes for both virtual machines to access memory.

What should you configure on each virtual machine?

A. Resource control

B. Memory weigh

t

C. Dynamic Memory

D. NUMA topology

Explanation:

Windows Server 2012introduced support for projecting a virtual NUMA topology into Hyper-V virtual machines. This capability can help improve the performance of workloads running on virtual machin

es that are configured with large amounts of memory.


Leave a Reply