PrepAway - Latest Free Exam Questions & Answers

which sequence should the tasks be deployed?

A customer wants to set up a QFX3000-M QFabric system, which includes Director devices,
Interconnect devices, Node devices, and EX4200 switches. The network engineer wants to know the
proper task sequence when configuring the QFabric system for the first time. In which sequence
should the tasks be deployed?

PrepAway - Latest Free Exam Questions & Answers

A.
Deploy the Director group, control plane network, and then the system components.

B.
Deploy the system components, Director group, and then the control plane network.

C.
Deploy the control plane network, Director group, and then the system components.

D.
Deploy the system components, Director group, and then the control plane network.