PrepAway - Latest Free Exam Questions & Answers

Which of the following is an example of the test closure activity indicated as "lessons learned"?

Which of the following is an example of the test closure activity indicated as “lessons learned”?

PrepAway - Latest Free Exam Questions & Answers

A.
Archive all the test results of the acceptance testing phase

B.
Deliver a list of the open defects of a software product released into production to the service
desk team

C.
Participate in a meeting at the end of a project aimed at better managing the events and
problems of future projects

D.
Deliver an automated regression test suite, used during the system test phase of a software
product released into production, to the team responsible for maintenance testing

Explanation:

One Comment on “Which of the following is an example of the test closure activity indicated as "lessons learned"?


Leave a Reply