Which of the following methodologies is appropriate for planning and controlling activities and resources in a

Which of the following methodologies is appropriate for planning and controlling activities and
resources in a system project?

PrepAway - Latest Free Exam Questions & Answers

A.
Gantt charts

B.
Program evaluation review technique (PERT)

C.
Critical path methodology (CPM)

D.
Function point analysis (FP)

Explanation:
A Gantt chart is a popular type of bar chart showing the interrelationships of how
projects, schedules, and other time-related systems progress over time.
Not B:
Program Evaluation and Review Technique – (PERT) A method used to size a software product
and calculate the Standard Deviation (SD) for risk assessment. The PERT equation (beta
distribution) estimates the Equivalent Delivered Source Instructions (EDSIs) and the SD based on
the analyst’s estimates of the lowest possible size, the most likely size, and the highest possible
size of each computer program component (CPC).
http://computing-dictionary.thefreedictionary.com/