Which of the following methodologies is appropriate for planning and controlling activities and
resources in a system project?

A.
Gantt charts
B.
Program evaluation review technique (PERT)
C.
Critical path methodology (CPM)
D.
Function point analysis (FP)
Explanation:
A Gantt chart is a popular type of bar chart showing the interrelationships of how projects,
schedules, and other time-related systems progress over time. Not B: Program Evaluation and
Review Technique – (PERT) A method used to size a software product and calculate the Standard
Deviation (SD) for risk assessment. The PERT equation (beta distribution) estimates the Equivalent
Delivered Source Instructions (EDSIs) and the SD based on the analyst’s estimates of the lowest
possible size, the most likely size, and the highest possible size of each computer program
component (CPC). http://computing-dictionary.thefreedictionary.com/