Which of the following is not used as a cost estimating technique during the project planning stage?

A.
Delphi technique
B.
Expert Judgment
C.
Program Evaluation Review Technique (PERT) charts
D.
Function points (FP)
Explanation:
“Methods and techniques for cost estimation: Experts’ evaluation Delphi Bottom-up approaches