Which of the following is NOT one of the primary goals of a BIA?

A.
Downtime estimation
B.
Criticality prioritization
C.
Personnel safety
D.
Resource requirements
Explanation:
The correct answer is Personnel safety. Personnel safety is the primary priority of
BCP and DRP, not BIA.
Personnel safety is the primary priority of
BCP and DRP, not BIA.