Which of the following is NOT a Software CMM maturity level?

Which of the following is NOT a Software CMM maturity level?

PrepAway - Latest Free Exam Questions & Answers

A.
Initial

B.
Behavioral

C.
Managed

D.
Repeatable

Explanation:
The word behavioral is a distracter. The five software process maturity
levels are:
Initial the software process is ad hoc and most processes are
undefined.
Repeatable fundamental project management processes are in
place.
Defined the software process for both management and
engineering functions is documented, standardized, and
integrated into the organization.
Managed the software process and product quality are
measured, understood, and controlled.
Optimizing continuous process improvement is being
performed.