PrepAway - Latest Free Exam Questions & Answers

Which of the following configuration management system processes keeps track of the changes so that the latest

Which of the following configuration management system processes keeps track of the changes
so that the latest acceptable configuration specifications are readily available?

PrepAway - Latest Free Exam Questions & Answers

A.
Configuration Control

B.
Configuration Status and Accounting

C.
Configuration Verification and Audit

D.
Configuration Identification

Explanation:
The configuration status accounting procedure is the ability to record and report on
the configuration baselines associated with each configuration item at any moment of time. It
supports the functional and physical attributes of software at various points in time, and performs
systematic control of accounting to the identified attributes for the purpose of maintaining software
integrity and traceability throughout the software development life cycle. The configuration status
and accounting process keeps track of the changes so that the latest acceptable configuration
seek to establish a high level of confidence in how well the Configuration Management activity is
management. Configuration control is a set of processes and approval stages required to change
a configuration item’s attributes and to re-baseline them. It supports the change of the functional
and physical attributes of software at various points in time, and performs systematic control of
process of identifying the attributes that define every aspect of a configuration item. A
configuration item is a product (hardware and/or software) that has an end-user purpose. These
attributes are recorded in configuration documentation and baselined. Baselining an attribute
forces formal configuration change control processes to be effected in the event that these
attributes are changed.