Which of the following alternative business recovery strategies would be LEAST appropriate in a
large database and on-line communications network environment where the critical business
continuity period is 7 days?

A.
Hot site
B.
Warm site
C.
Duplicate information processing facilities
D.
Reciprocal agreement