Which choice below is NOT a common result of a risk analysis?

Which choice below is NOT a common result of a risk analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
Valuations of critical assets

B.
Definition of business recovery roles

C.
Likelihood of a potential threat

D.
Adetailed listing of relevant threats

Explanation:
The correct answer is “Definition of business recovery roles”. The first three answers are common
results
of a risk analysis to determine the probability and effect of threats to
company assets. Answer “Definition of business recovery roles”is a distracter.