PrepAway - Latest Free Exam Questions & Answers

What component of the change management system is responsible for evaluating, testing, and documenting changes

What component of the change management system is responsible for evaluating, testing, and
documenting changes created to the project scope?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Management Information System

B.
Integrated Change Control

C.
Configuration Management System

D.
Scope Verification

Explanation:
The change management system is comprised of several components that guide
the change request through the process. When a change request is made that will affect the
project scope. The Configuration Management System evaluates the change request and
documents the features and functions of the change on the project scope.


Leave a Reply