Which of the following is a continuity plan test that uses actual resources to simulate a system
crash to cost-effectively obtain evidence about the plan’s effectiveness?
A.
Paper test
B.
Post test
C.
Preparedness test
D.
Walk-through
Explanation:
A preparedness test is a localized version of a full test, wherein resources are expended in the
simulation of a system crash. This test is performed regularly on different aspects of the plan and
can be a cost-effective way to gradually obtain evidence about the plan’s effectiveness. It also
provides a means to improve the plan in increments.