During an audit of a business continuity plan (BCP), an IS auditor found that, although all departments were
housed in the same building, each department had a separate BCP. The IS auditor recommended that the
BCPs be reconciled. Which of the following areas should be reconciled FIRST?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Evacuation plan
B.
Recovery priorities
C.
Backup storages
D.
Call tree
Explanation:
Protecting human resources during a disaster-related event should be addressed first. Having separate BCPs
could result in conflicting evacuation plans, thus jeopardizing the safety of staff and clients. Choices B, C and D
may be unique to each department and could be addressed separately, but still should be reviewed for possible
conflicts and/or the possibility of cost reduction, but only after the issue of human safety has been analyzed.