When should application controls be considered within the system-development process?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
After application unit testing
B.
After application module testing
C.
After applications systems testing
D.
As early as possible, even in the development of the project’s functional specifications
Explanation:
Application controls should be considered as early as possible in the system-development process, even
in the development of the project’s functional specifications.