What often results in project scope creep when functional requirements are not defined as well as
they could be?

A.
Inadequate software baselining
B.
Insufficient strategic planning
C.
Inaccurate resource allocation
D.
Project delays
Explanation:
Inadequate software baselining often results in project scope creep because
functional requirements are not defined as well as they could be.