With the objective of mitigating the risk and impact of a major business interruption, a
disasterrecovery plan should endeavor to reduce the length of recovery time necessary, as well as
costs associated with recovery. Although DRP results in an increase of pre-and post-incident
operational costs, the extra costs are more than offset by reduced recovery and business impact
costs. True or false?

A.
True
B.
False
Explanation:
With the objective of mitigating the risk and impact of a major business interruption,
a disaster-recovery plan should endeavor to reduce the length of recovery time necessary and the
costs associated with recovery. Although DRP results in an increase of pre-and post-incident
operational costs, the extra costs are more than offset by reduced recovery and business impact
costs.