During the development of an application, the quality assurance testing and user acceptance
testing were combined. The MAJOR concern for an IS auditor reviewing the project is that there
will be:

A.
increased maintenance.
B.
improper documentation of testing.
C.
inadequate functional testing.
D.
delays in problem resolution.
Explanation:
The major risk of combining quality assurance testing and user acceptance testing is that
functional testing may be inadequate. Choices A, B and D are not as important.