If an IS auditor observes that individual modules of a system perform correctly in development
project tests, the auditor should inform management of the positive results and recommend
further:

A.
Documentation development
B.
Comprehensive integration testing
C.
Full unit testing
D.
Full regression testing
Explanation:
If an IS auditor observes that individual modules of a system perform correctly in
development project tests, the auditor should inform management of the positive results and
recommend further comprehensive integration testing.