Following best practices, formal plans for implementation of new information systems are
developed during the:

A.
development phase.
B.
design phase.
C.
testing phase.
D.
deployment phase.
Explanation:
Planning for implementation should begin well in advance of the actual implementation date. A
formal implementation plan should be constructed in the design phase and revised as the
development progresses.