When will the quantitative risk analysis process need to be repeated?

Fred is the project manager of the PKL project. He is working with his project team to complete the
quantitative risk analysis process as a part of risk management planning.
Fred understands that once the quantitative risk analysis process is complete, the process will
need to be completed again in at least two other times in the project. When will the quantitative
risk analysis process need to be repeated?

What technique will you use with this simulation?

CORRECT TEXT
You are the project manager of the AMD project for your organization. In this project, you are
currently performing quantitative risk analysis. The tool and technique you are using is simulation
where the project model is computed many times with the input values chosen at random for each
iteration. The goal is to create a probability distribution from the iterations for the project schedule.
What technique will you use with this simulation?