Given a job with priority GO/101, which two actions prevent the job from running? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
change job priority to HI/100

B.
change job priority to zero(0)/HOLD

C.
set limit to zero (0) on the workstation

D.
set limit to GO/101 on the workstation

E.
set fence to GO/101 on the workstation

Explanation: