What is happening to a job in a HOLD state marked with a [P] in the Deps column in the output of
the conman showjob command?
A.
The job is waiting for a prompt dependency to be released.
B.
The job cannot start because the maxi mum number of dependencies that can be set was
exceeded.
C.
A predecessor for the job has not yet been included in the preproduction plan or in the
production plan.
D.
A predecessor for the job exists in the preproduction plan but it has not yet been included in the
production plan.
Explanation: