Which part of the TDA process would ensure that there is enough power in the customer location to operate the

A customer has been quoted a DS8800. Which part of the TDA process would ensure that there is enough power in the customer location to operate the system?

PrepAway - Latest Free Exam Questions & Answers

A.
Pre-sale

B.
Post-sale

C.
Pre-install

D.
Post-install

Explanation: