An administrator with an HMC managed POWER7 system needs to perform a concurrent update
to server firmware. Which co-requisites and/or prerequisites should the administrator consider as
part of the planning process?

PrepAway - Latest Free Exam Questions & Answers

A.
Available flash storage on the system FSP

B.
IBM i, Licensed Internal Code PTE5, and HMC code level

C.
Ability’ of the HMC to attach to the Internet and the IBM Support ETP site for the download

D.
Service window to place the system partitions into restricted state and perform a platform IPL