PrepAway - Latest Free Exam Questions & Answers

What is the likely reason that the run time did not decrease?

A batch job runs daily in the QBATCH subsystem with a run priority of 50. The job normally takes
an hour to complete and no other batch jobs run during this time.
The administrator needs to reduce the run time and requests the run priority be lowered to 40.
However1 after the change, run time does not decrease.
What is the likely reason that the run time did not decrease?

PrepAway - Latest Free Exam Questions & Answers

A.
The run priority applies to only interactive jobs.

B.
D82 Symmetric Multiprocessing has not been installed.

C.
The run priority represents only the relative importance of the job.

D.
The system value QPFRADJ (Performance Adjustment) is set to “No adjustment.”