A customer wants to implement a 3-site continuous copy solution with three D38800
systems. A three-site Business Continuity (BC) license and TotalStorage Productively
Center for Replication (TPC-R) are already installed.
Which action should be completed before using the TPC-R GUI to configure the
Metro/Global Mirror?

A.
Select the action Start H1 -’H2->H3
B.
Configure the CIMON agent on the DSS800
C.
Add copy sets to the Metro/Global Mirror session
D.
Ensure paths exists between the 3 DS8800 systems