An administrator is attempting to configure a new deployment of 56 POWER7 Blades across 4
IBM BladeCenter H chassis. Each blade will be installed with an IVM and 2 LPARs.IVM is installed
and the administrator checks that both LHEA ports are reporting a Link State of “Up.” 2 LPARs are
created and the network traffic balanced by allocating one LHEA port to the first LPAR, the second
port to the other. After successfully installing the first LPAR via NIM, the administrator finds the
second LPAR fails to netboot. What should the administrator verify on the BladeCenter Chassis?

PrepAway - Latest Free Exam Questions & Answers

A.
That 4 power supplies (PSU) have been installed.

B.
That both the external LHEA ports have been cabled.

C.
That a secondary I/O module has been installed and cabled.

D.
That the Multi-Core Scaling (MCS) attribute is correctly set on both LHEA ports.