PrepAway - Latest Free Exam Questions & Answers

What is the most likely resolution for this issue?

As a result of an acquisition, an administrator is planning to consolidate some single-LPAR
POWER6 520 servers onto an existing POWER7 server.
The administrator is attempting to make these 520 systems HMC-managed.
The network connection between the 520 system and an existing operational HMC have been
verified and checked. However the POWER6 machines fail to appear on the HMC panels.
What is the most likely resolution for this issue?

PrepAway - Latest Free Exam Questions & Answers

A.
The POWER6 boxes need to be reset back to factory defaults.

B.
The Flexible Service Processor (FSP) needs to be reset on each POWER6 520.

C.
Upgrade to either PowerVM Standard or Enterprise edition.

D.
Power cycle the physical system.

Explanation:


Leave a Reply