PrepAway - Latest Free Exam Questions & Answers

what is the first step in this process?

Following an unscheduled power outage, the administrator needs to power up an IVM-managed
system. For the given system, what is the first step in this process?

PrepAway - Latest Free Exam Questions & Answers

A.
Physically press the appropriate button on the system.

B.
Physically disconnect and reconnect the power cable on the system.

C.
Log into the IVM using a Web Browser, select the managed-system and select the Power on
option from the Operations menu.

D.
Log into the HMC using a Web Browser, select the managed-system and select the Power on
option from the Operations menu.


Leave a Reply