A means of limiting production delays caused by equipment breakdown and repair is to:

A. Schedule production based on capacity planning.
B. Plan maintenance activity based on an analysis of equipment repair work orders.
C. Pre-authorize equipment maintenance and overtime pay.

D. Establish a preventive maintenance program for all production equipment.

Explanation:
A preventive maintenance program reduces equipment breakdowns and repairs.