Which of the following is NOT a purpose of the Closing a Project process?

A.
Plan the activities required to close a project
B.
Enable a comparison of the original objectives of a project against what was actually achieved
C.
Enable premature closure if the Project Board request that a project should no longer continue
D.
Provide a fixed point at which acceptance for the project product is confirmed
Explanation:
A