The Team Manager should check the [ ?

Identify the missing words in the following sentence.
The Team Manager should check the [ ? ] for any interfaces that must be maintained while
developing products.

PrepAway - Latest Free Exam Questions & Answers

A.
Project Product Description

B.
Project Plan

C.
Checkpoint Report

D.
Work Package