What product records any time tolerances agreed between the Project Manager and Team Manager?

What product records any time tolerances agreed between the Project Manager and Team
Manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Product Description

B.
Work Package

C.
Project Initiation Documentation

D.
Stage Plan

Explanation: