Which may be funded from a risk budget?

A.
Capturing identified threats and opportunities in the Risk Register
B.
Specific management responses to a project’s threats and opportunities
C.
Producing risk summaries for inclusion in Highlight Reports
D.
Any remaining open risks after the project has been closed