Identify the missing words in the following sentence.During the Initiating a Project process the [?]
before a project is authorized.

A.
minimum necessary is done to decide if a project is worthwhile
B.
aim is to establish sound foundations to achieve a successful project
C.
Project Brief is assembled and approved
D.
project approach appropriate for delivering a project is selected
B