What makes the bar become longer?
For a Sprint, progress is monitored in a burn-up chart with bars.
What makes the bar become longer?
what would your best advice be?
A 200 member project team is working on a large and complex system with multiple subsystems. They would like to start using the Agile Scrum methodology.
As a Scrum Master, what would your best advice be?
Which statement is true regarding this scenario?
A team estimates a Story using the Planning Poker technique. The team decides to allocate
five Story points to the Story, because the Developers estimated two points and the Testers
estimated three points.
Which statement is true regarding this scenario?
Why does the Daily Scrum need to be held at the same location and time?
Why does the Daily Scrum need to be held at the same location and time?
What is a Scrum-of-Scrums?
What is a Scrum-of-Scrums?
Why is planning poker an effective estimation technique?
Why is planning poker an effective estimation technique?
What term can be used to describe the traffic light?
A team decided to install a large traffic light in the team hall to indicate whether the latest
build was healthy (green), failing a few tests (orange) or failing high priority tests (red).
What term can be used to describe the traffic light?
Which is a statement of value as described in the Agile manifesto?
Which is a statement of value as described in the Agile manifesto?
What value (in days) should be used for planning?
During a Sprint Planning session, the team argues about the work estimates for a particular
story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?