A change process model should include…
A change process model should include:
1 – The steps that should be taken to handle the change with any dependences or co-processing
defined, including handling issues and unexpected events
2 – Responsibilities; who should do what, including escalation
3 – Timescales and thresholds for completion of the actions
4 – Complaints procedures
Which of the following is an objective of Release and Deployment Management?
Which of the following is an objective of Release and Deployment Management?
Which process is responsible for eliminating recurring incidents and minimizing the impact of incidents that c
Which process is responsible for eliminating recurring incidents and minimizing the impact of
incidents that cannot be prevented?
Which phase of the ITIL lifecycle provides the following benefit: The Total Cost of Ownership (TCO) of a servi
Which phase of the ITIL lifecycle provides the following benefit: The Total Cost of Ownership
(TCO) of a service can be minimized if all aspects of the service, the processes and the
technology are considered during development?
which of the following?
A Service Design Package should be produced for which of the following?
1. A new IT service
2. A major change to an IT service
3. An Emergency Change to an IT service
4. An IT service retirement
Which of the following BEST describes a Problem?
Which of the following BEST describes a Problem?
which of the following?
A process owner is responsible for which of the following?
1. Documenting the process
2. Defining process Key Performance Indicators (KPIs)
3. Improving the process
4. Ensuring process staff undertake the required training
Contracts are used to define:
Contracts are used to define:
Products refers to:
In the phrase “People, Processes, Products and Partners”. Products refers to:
which processes?
Service Transition contains detailed descriptions of which processes?