The customer has not followed EMC best practices when cabling their VS2 VPLEX engine. You
are asked how to re-cable the engine to adhere to best practices. What is your response?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Swap port 00 with port 01 of both director A and director B.
B.
Swap port 02 with port 03 of both director A and director B.
C.
Swap port 00 with port 01 of director B.
D.
Swap port 00 with port 01 of director A.
Explanation:
A.
Swap port 00 with port 01 of both director A and director B.
0
0
Care to explain why? Stop posting just what the answer is.
0
0
The following are recommended:
Dual fabric designs for fabric redundancy and HA should be implemented to avoid a single point of failure. This provides data access even in the event of a full fabric outage.
Each VPLEX director will physically connect to both fabrics for both host (front-end) and storage (back-end) connectivity. Hosts will connect to both an A director and B director from both fabrics for the supported HA level of connectivity as required with the NDU pre-checks
0