Which of the following would be considered a project?

Which of the following would be considered a project?

PrepAway - Latest Free Exam Questions & Answers

A.
The daily backup of scanned images

B.
Adding a new user to the document management security database

C.
The continual improvement of a business process

D.
The implementation of an enterprise content system