A project team member has identified a required change to one of their assigned tasks. The
change would alter the order in which other tasks must be completed. Which of the following
should be done NEXT?

A.
Perform an impact analysis
B. Implement the change
C.
Update the change registry
D.
Document the change
I believe the answer is A
0
0
I believe this is D.
This is the order I have:
-Assign a request
-record in change log
Impact analysis
-submit request
(approved or not)
-inform stake holder of decision
0
0