Which of the following is the cost of the resources?

A project has two resources scheduled to work 40 hours a week for four weeks, both at
$85.00 an hour. One resource called in sick for 16 hours, while the other resource worked
four hours additional. Which of the following is the cost of the resources?

PrepAway - Latest Free Exam Questions & Answers

A.
$27,540

B.
$25,840

C.
$26,180

D.
$27,200

Explanation: