The project manager should FIRST schedule a meeting with:

A project has been going on for three weeks, and the project manager notices that
Resource A is beginning to fall behind schedule. The project manager should FIRST
schedule a meeting with:

PrepAway - Latest Free Exam Questions & Answers

A.
The project stakeholders to communicate the delay.

B.
Resource A to confirm estimates.

C.
The other team members to make up the schedule slippage.

D.
The manager of Resource A for corrective action.