A project manager has contracted with a landscaping service to complete the grounds work
on a new building. The landscaper provides the project manager with the following cost
estimate: $150 per hour, estimated time to completion=40 hours The landscaper has
completed 35 hours of work. Which of the following is the Earned Value of this portion of the
project?
A.
$6000
B.
$750
C.
$3000
D.
$5250