The project has spent $5,000 to date. The earned value of the project is $7,500. Using
earned value management, which of the following is correct?

A.
The project is under budget.
B.
The project is ahead of schedule.
C.
The project is over budget
D.
The project is behind schedule.
The project may not have yet exceeded the budget. However, there isn’t enough information to know if it is under budget at the current percent of completion.
Kind of an unfair question.
0
0
More, part of the new 115Q PK0-004 dumps FYI:
https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U
Best Regards!
0
0
Besides, part of new 115Q PK0-004 dumps are available here:
https://drive.google.com/open?id=0B-ob6L_QjGLpWmFpamxGZTNmX0U
Best Regards!
0
0