The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000
AC = 90,000 Based on this scenario, calculate the schedule variance.

A.
120,000
B.
10,000
C.
-80,000
D.
-70,000
You must be logged in to post a comment.
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV)